19 men working 12 hours a day complete a piece of work in 21 days. In how many days can 12 men working 7 hours a day complete the same work?

1. 19 men working 12 hours a day complete a piece of work in 21 days. In how many days can 12 men working 7 hours a day complete the same work?

 