14,988+ Questions · 21 Subjects · Free to Practice

4 men working 12 hours a day complete a piece of work in 10 days. In how many days can 16 men working 10 hours a day complete the same work?

1. 4 men working 12 hours a day complete a piece of work in 10 days. In how many days can 16 men working 10 hours a day complete the same work?

 

Beyond the answer

    Leave a Reply

    Discover more from MCQ Questions

    Subscribe now to keep reading and get access to the full archive.

    Continue reading