ITER: What India Gets if Fusion Power Works

Practice: 8 MCQs

At a glance

The giant fusion experiment India helps build

01 PlaceCadarache, southern France. Seven Members share the project.
02 GoalQ of at least 10: 500 MW of fusion power from 50 MW of heating.
03 IndiaAbout 9.1 percent of the cost, paid mostly as parts. The cryostat is its best-known part.
04 DatesResearch operation in 2034 and deuterium-tritium operation in 2039.
  • ITER is fusion. India thorium plan is fission.
  • ITER is an experiment. It will not make electricity.
  • The 2016 question: the immediate gain is the ability to build fusion reactors.
FusionLight atoms join to make a heavier atom and release energy.
TokamakA doughnut-shaped machine that holds hot plasma with magnetic fields.
PlasmaA gas so hot that electrons break away from the nuclei.
CryostatThe steel chamber that keeps the magnets very cold.

ITER is a giant fusion experiment being built in southern France. India is one of its seven members. This lesson explains what fusion is and what ITER wants to prove. It also shows what India builds for ITER and what India gets back. Where sources give different numbers, the article says so.

Contents
  1. What fusion is
  2. What ITER is
  3. What ITER must prove
  4. Delays and cost
  5. India's part and gains
  6. India at home and the 2016 question
  7. The exam checklist
  8. 4 questions to think through
  9. 7 understanding checks
  10. Related topics
  11. 8 practice MCQs

What is fusion, and why is it so hard to do on Earth?

Fusion is the reaction that powers the Sun. Making it work in a machine needs extreme heat and a way to hold the hot gas in place.

1. What is nuclear fusion?

Fusion means light atoms join to make a heavier atom. In the Sun, hydrogen nuclei collide and fuse into helium. A tiny bit of mass is lost in the process. That lost mass turns into a very large amount of energy.

  • Fusion is the energy source of the Sun and the stars.
  • The Sun’s core is at about 15,000,000 °C.
  • The Sun turns about 600 million tonnes of hydrogen into helium every second.
What fusion isLight atoms join, lose a little mass and release energy.Light atomsJoin to make a heavier atomA little massIs lost in the processThe lost massBecomes a large amount of energyNatural exampleThe Sun and the stars
The Sun runs on this reaction every second. Original explanatory diagram.

2. How hot must a fusion machine get?

On Earth the machine must be much hotter than the Sun’s core. ITER says deuterium-tritium fusion needs about 150,000,000 °C in the laboratory. That is ten times the temperature at the Sun’s core.

The live article says “many times hotter than the Sun’s core”. That is correct. The exact figure is about ten times.

Three conditions must be met together.

  • Very high temperature.
  • Enough plasma particles packed together so that collisions happen.
  • Enough confinement time, meaning the plasma is held in place long enough.
How hotITER plasma must be ten times hotter than the Sun's core.Sun's coreAbout 15,000,000 °CITER plasmaAbout 150,000,000 °CDifferenceAbout ten times hotterThree needsHeat, density, confinement time
Heat alone is not enough. Original explanatory diagram.

3. What is plasma, and what is a tokamak?

At such heat, electrons break away from the nuclei. The gas becomes a plasma. It is often called the fourth state of matter.

A tokamak holds the plasma with strong magnetic fields. The word comes from a Russian phrase meaning “toroidal chamber with magnetic coils”. Its vacuum chamber is shaped like a doughnut.

The plasma never touches the walls. Magnetic coils keep it away from them. Heat from the fusion reaction is absorbed in the walls.

What a tokamak doesA tokamak holds hot plasma with magnetic fields.PlasmaFourth state of matterHeld byStrong magnetic fieldsChamber shapeDoughnutHeat is absorbed byThe walls
The plasma floats clear of the walls. Original explanatory diagram.
Inside the doughnut-shaped vacuum vessel of the JET tokamak, lined with metal wall tiles.
Interior of the JET tokamak vacuum vessel, lined with metal wall tiles, by EUROfusion (CC BY 4.0), Wikimedia Commons.
True or False: In a tokamak, magnetic fields keep the hot plasma away from the chamber walls.

4. Which fuel does fusion use, and where does it come from?

The easiest reaction uses two forms of hydrogen. They are deuterium (D) and tritium (T). The D-T reaction gives the most energy at the “lowest” temperature. It makes one helium nucleus and one neutron.

  • Deuterium can be taken from any water. Each cubic metre of seawater holds about 33 grams.
  • Tritium is very rare in nature.
  • Tritium has a half-life of 12.3 years.
  • Today the main source of tritium is heavy-water fission reactors, such as CANDU types. India operates this kind of reactor.

Future plants must make their own tritium. They will do it from lithium inside the machine.

The fuelDeuterium is plentiful and tritium is scarce.Deuterium33 g in a cubic metre of seawaterTritiumRare, half-life 12.3 yearsTritium todayFrom heavy-water fission reactorsFuture plantsBreed it from lithium
One fuel is plentiful and the other is scarce. Original explanatory diagram.

5. How is fusion different from fission?

Fission splits heavy atoms. Fusion joins light atoms. They are different reactions.

  • Fission is a chain reaction. A fission core holds several tonnes of radioactive fuel.
  • Fusion is not a chain reaction. The whole ITER system holds only a few kilograms of tritium.
  • Only a few grams of fuel react at any moment.
  • A runaway reaction is impossible. If anything goes wrong, the plasma cools and the reaction stops.

India’s thorium plans are about fission. Fusion is a separate technology.

Fission and fusionFission splits heavy atoms and fusion joins light atoms.FissionSplits heavyatomsChainreactionTonnes of fuelin the coreFusionJoins lightatomsNo chainreactionFew kg oftritium in ITER
Thorium plans belong in the left box. Original explanatory diagram.

6. Is fusion free of radioactive waste?

Not quite. The live article says fusion has “no long-lived radioactive waste”. ITER’s wording is narrower. It says fusion plants make no high-activity, long-life waste.

  • The “burnt” fuel is helium, which is not radioactive.
  • Tritium is radioactive, but only a few grams are used at a time.
  • Fast neutrons make the vessel materials radioactive over time.
  • That waste is rated very low, low or medium activity.
  • Most of its radioisotopes have half-lives under ten years.
  • ITER expects the materials to be recyclable within about 100 years.

So the safe line is “no high-activity, long-life waste”. Do not say “no radioactive waste”.

Fusion wasteFusion makes no high-activity, long-life waste.Burnt fuelHelium, not radioactiveTritiumRadioactive, a few grams at a timeVessel materialsMade radioactive by fast neutronsTheir wasteVery low, low or medium activityRecyclingPossible in about 100 years
Narrow wording is the safe wording. Original explanatory diagram.
True or False: Fusion plants make no radioactive waste at all.

What is ITER, and who is building it?

ITER is a research machine, not a power plant. It sits in France but belongs to seven partners.

7. What is ITER, and where is it?

ITER is a large experiment to prove fusion can work as a big, carbon-free energy source. The name is Latin for “The Way”. It is being built at Cadarache, near Saint-Paul-lez-Durance in southern France. The site is about 70 km north-west of Marseille. It covers 42 hectares.

When finished, it will be the world’s largest tokamak. It will have about six times the plasma volume of the biggest machine running today.

ITER at a glanceBasic identity of the project.NameLatin for The WaySiteCadarache, southern FranceArea42 hectaresLocation70 km north-west of MarseilleWhen finishedWorld's largest tokamak
Basic identity of the project. Original explanatory diagram.
The ITER tokamak complex under construction, with a round concrete structure surrounded by scaffolding.
ITER tokamak complex under construction, April 2018, by Oak Ridge National Laboratory (CC BY 2.0), Wikimedia Commons.

8. Who are the members, and who pays what?

There are seven ITER Members. They are China, the European Union, India, Japan, Korea, Russia and the United States.

  • Europe pays the largest share of construction cost, about 45.6 percent.
  • The other six pay about 9.1 percent each. That includes India.
  • About nine-tenths of the value arrives as in-kind parts, not cash.
  • All Members share the results and the intellectual property.
Who paysEurope pays the most and six Members pay equal shares.EuropePays about45.6 percentOther sixPay about9.1 percent eachIndia isone of them
Most of the value arrives as parts. Original explanatory diagram.

9. When did ITER begin?

The idea of a joint fusion experiment dates from 1985. The project then moved in steps.

  • 2005: the decision to site ITER in France.
  • 2006: the ITER Agreement was signed.
  • 2007: the ITER Organization was formally created.
  • 2010: building work began on the main site.
  • 2012: ITER became a licensed nuclear installation under French law.
  • 2020: machine assembly began.

India became a full partner in December 2005. It signed the 2006 agreement with the other six. That is why the live article can call India a founding member.

From idea to assemblyKey years of the project.1985Idea of a joint experiment2005Decision to site ITER in France2006ITER Agreement signed2007ITER Organization created2010Building work began2012Licensed nuclear installation2020Machine assembly began
Steps from idea to assembly. Original explanatory diagram.

10. What does the ITER machine look like, and will it make electricity?

ITER is a doughnut-shaped tokamak ringed by superconducting magnets. Its main parts are listed below.

  • Plasma volume: 840 cubic metres.
  • Vacuum vessel: about 19.4 m across and about 5,200 tonnes.
  • Toroidal field magnets: 18 D-shaped coils, each 330 tonnes.
  • Cryostat: a steel outer chamber that keeps the magnets very cold. India built it.

ITER will not make electricity. It will heat plasma and measure the fusion power. Machines after ITER must turn that heat into power.

Main partsKey sizes of the ITER machine.Plasma volume840 cubic metresVacuum vessel19.4 m across, 5,200 tonnesMagnets18 D-shaped coils, 330 tonnes eachCryostatBuilt by IndiaElectricityNone; ITER only measures power
Sizes of the main parts. Original explanatory diagram.
A cutaway scale model of the ITER tokamak showing its internal layers and the central column.
Cutaway model of the ITER tokamak, by Johannes Reimer (CC BY 4.0), Wikimedia Commons.

What is ITER trying to prove, and how do other machines compare?

ITER’s main goal is a tenfold power gain. Other machines have set records, but none has reached ITER’s target in a tokamak.

11. What does Q greater than or equal to 10 mean?

Q is the ratio of fusion power made to heating power put in. Q = 1 is breakeven. At breakeven the plasma gives out as much fusion power as it takes in.

ITER is designed for Q of at least 10. That means:

  • 50 MW of heating power goes in.
  • 500 MW of fusion power comes out of the plasma.

ITER says no magnetic-confinement machine has yet reached Q = 1.

What Q meansQ compares fusion power made with heating power put in.QFusion power out over heating power inQ = 1BreakevenITER designQ of at least 10Heating in50 MWFusion out500 MW
A tenfold gain is the headline target. Original explanatory diagram.
True or False: A Q of 1 means the plasma gives out as much fusion power as the heating power put in.

12. How long must the pulses last?

The 2024 press conference gave the goal as 500 MW for 400 seconds. The ITER FAQ gives a range of 400 to 600 seconds. Use 400 seconds as the safe figure, and know the range.

ITER will also test a second mode. It is a steady-state run at a lower gain of Q = 5.

Pulse lengthThe pulse goal is 400 seconds, and the FAQ gives a range.2024 goal500 MW for400 secondsUse this asthe safe figureFAQ range400 to 600secondsSecond mode:steady stateat Q = 5
Two sources, one safe figure. Original explanatory diagram.

13. What is a burning plasma, and what is tritium breeding?

In a burning plasma, the helium nuclei made by fusion supply enough heat to keep the plasma hot. Outside heating is then needed much less. ITER’s main aim is to study this.

ITER will also test tritium breeding. Neutrons hit lithium and make tritium. The process is meant to run inside the vacuum vessel.

  • The test uses lithium-6.
  • The world has too little tritium to fuel many plants.
  • Worldwide stock from heavy-water reactors does not exceed about 20 kilograms in any year.
  • That stock is just enough to fuel ITER’s planned D-T years.
Burning plasmaHelium from fusion keeps the plasma hot.Burning plasmaHelium nuclei keep it hotResultLess outside heating neededTritium breedingNeutrons hit lithium-6World stockNot above about 20 kg a yearWhy test itPlants must make their own tritium
Breeding is a test, not yet a fact. Original explanatory diagram.

14. What did JET achieve?

JET was a European tokamak at Culham in the UK. It was a large magnetic-fusion machine.

  • In 1997, JET made 16 MW of fusion power from 24 MW of heating. That is Q of 0.67.
  • Its fusion energy record rose from 22.7 MJ (1997) to 59 MJ (2022 report).
  • In 2024, EUROfusion reported a new record of about 69 MJ, from only 0.21 milligrams of fuel.

JET never reached Q = 1. The records measure different things, so do not mix them.

JET recordsJET made magnetic-fusion records but never reached Q = 1.199716 MW from 24 MW, Q of 0.67Energy record, 199722.7 MJEnergy record, 2022 report59 MJ2024 recordAbout 69 MJNever reachedQ = 1
Each record counts a different thing. Original explanatory diagram.
The JET fusion experiment in 1991, a tangle of orange frames, pipes and machinery around the central torus.
The JET magnetic fusion experiment in 1991, by EFDA JET (CC BY-SA 3.0), Wikimedia Commons.
True or False: JET reached Q = 1 in a magnetic-confinement tokamak.

15. What was the NIF ignition result of 2022?

The National Ignition Facility (NIF) is in the United States. It uses lasers, not magnets. On 5 December 2022 it gave 2.05 MJ of laser energy to a fuel target. The fusion output was 3.15 MJ.

The US Department of Energy called this the first controlled fusion experiment to produce more energy than the laser energy used to drive it.

Do not mix this with ITER’s goal. NIF counts laser energy on the target. It does not count the large power drawn from the grid to run the lasers.

NIF and ITERNIF uses lasers and ITER uses magnets.NIF, lasersLaser energy in:2.05 MJFusion out:3.15 MJDate:5 Dec 2022ITER, magnetsHeating in:50 MWFusion out:500 MWDesign Q:at least 10
The two machines count their input differently. Original explanatory diagram.
Inside the large spherical target chamber of the National Ignition Facility, with a positioner arm and a technician.
Interior of the National Ignition Facility target chamber, Lawrence Livermore National Laboratory (public domain), via Wikimedia Commons.

16. What about China's EAST and the SPARC project?

EAST is China’s superconducting tokamak at Hefei. On 20 January 2025 it held a high-confinement plasma for 1,066 seconds. The earlier record was 403 seconds, also set by EAST in 2023. This test shows long duration. It does not show energy gain.

SPARC is a private tokamak built by Commonwealth Fusion Systems in the United States. The company says its first goal is Q above 1. It says SPARC will reach that in 2027. That is a company claim. No SPARC result had been reported when this was checked.

EAST and SPARCEAST shows long duration and SPARC is a company claim.EAST, China1,066 secondson 20 Jan 2025Old record:403 secondsShows duration,not gainSPARC, privateBuilt by CFSin the USCompany goal:Q above 1, in 2027No resultreported yet
Duration and gain are different tests. Original explanatory diagram.
Inside the EAST tokamak vessel, with labels marking tungsten, molybdenum and graphite wall regions.
Inside the EAST tokamak vacuum vessel, labelled with wall materials, by Xiang Gao et al. (CC BY 3.0), Wikimedia Commons.

Why has ITER been delayed, and what does it cost?

ITER is far behind its first plan. The cost figures also differ by source.

17. What was the old schedule?

The 2016 baseline had two main dates.

  • First plasma: December 2025.
  • Start of deuterium-tritium operation: 2035.

First plasma would have been a short test of a partly built machine. The ITER Director-General called it “rather symbolic” in 2024, according to Physics World.

The old scheduleThe 2016 baseline had two main dates.Baseline2016First plasmaDecember 2025D-T operation2035First plasma wasA short test only
This plan is now out of date. Original explanatory diagram.

18. What is the current schedule?

The ITER Council approved a new baseline approach in November 2024. It starts research with a fuller machine.

  • 2034: Start of Research Operation, with hydrogen and deuterium plasmas.
  • 2036: full magnetic energy. This is a three-year delay.
  • 2039: start of deuterium-tritium operation. This is a four-year delay.

The new plan drops the early symbolic first plasma. The project says its mission goals have not changed.

The new scheduleThe ITER Council approved a new baseline in November 2024.November 2024New baseline approved2034Start of Research Operation2036Full magnetic energy, 3 years later2039D-T operation, 4 years later
New dates replace the old ones. Original explanatory diagram.

19. Why was ITER delayed?

Several causes added up.

  • The Covid-19 pandemic caused supply-chain and quality-control delays.
  • Cracks were found in water pipes that cool the thermal shields.
  • In early 2022 the French nuclear regulator briefly halted assembly over radiation shielding.
  • Some first-of-a-kind components needed repair.

ITER’s FAQ also lists older causes of rising cost. The 2008 design review added new coils. The number of Members grew from four to seven. Steel and concrete prices rose.

Why it slippedSeveral causes added up.Covid-19Supply-chain and quality delaysCooling pipesCracks in thermal-shield pipesEarly 2022Regulator briefly halted assemblyComponentsFirst-of-a-kind parts needed repairOlder causes2008 review, more Members, prices
The delay has more than one cause. Original explanatory diagram.
Aerial view of the ITER fusion reactor construction site in France
Aerial view of the ITER site at Cadarache, by Oak Ridge National Laboratory (CC BY 2.0), Wikimedia Commons.

20. How much does ITER cost?

No single number is right. Most parts are built in-kind by Members, who do not have to publish their real costs.

  • The first estimate, from the 2001 design, was EUR 5 billion for construction.
  • ITER’s FAQ says the cost of construction for the seven Members was once evaluated at about EUR 13 billion.
  • In 2024, the Director-General said the new plan adds about EUR 5 billion for the ITER Organization. Members were still reviewing it.
  • Scientific American reports the latest official estimate at more than 20 billion euros (about 22 billion dollars). Physics World says “tens of billions of euros”.

For an exam, say ITER costs tens of billions and is far over its first estimate.

Cost estimatesCost figures differ by source.2001 designEUR 5 billionITER FAQAbout EUR 13 billion2024 plan addsAbout EUR 5 billionScientific AmericanOver EUR 20 billion (about $22 billion)
Quote tens of billions, not one number. Original explanatory diagram.
True or False: All sources agree on one exact total cost for ITER.

What does India build for ITER, and what does India get back?

India’s part is built by the Institute for Plasma Research and Indian companies. The biggest piece is the cryostat.

21. When did India join, and who manages its share?

India joined ITER as a full partner in December 2005. The Institute for Plasma Research (IPR) in Gandhinagar manages India’s part. IPR is an aided institute of the Department of Atomic Energy (DAE).

IPR’s ITER arm is called ITER India. It is the Indian Domestic Agency. It was formed as a specially empowered body in November 2007.

India joinsIndia became a partner in 2005.December 2005India becomes a full partner2006Signs the ITER AgreementNovember 2007ITER India is formedManagerInstitute for Plasma ResearchHomeGandhinagar
IPR sits under the Department of Atomic Energy. Original explanatory diagram.

22. What share does India pay, and how?

India pays about 9.1 percent of construction cost. Most of it is not cash. It is delivered as finished parts, called in-kind contributions.

ITER describes India’s work as 14 procurement packages. The cryostat is the largest of them. Indian industry builds the parts under contracts from ITER India.

India's shareIndia pays about 9.1 percent, mostly in parts.India paysAbout 9.1percentMostly asin-kind partsIndia's work14 procurementpackagesThe cryostatis the largest
Parts, not cash, are the main payment. Original explanatory diagram.

23. What is the cryostat, and who built it?

The cryostat is a huge stainless-steel vacuum chamber around the ITER vessel and magnets. It keeps the magnets cold. ITER calls it the largest stainless steel high-vacuum pressure chamber ever built.

  • Volume: 16,000 cubic metres.
  • Weight: 3,850 tonnes.
  • Made by Larsen & Toubro at Hazira.
  • Planned to ship from India in 54 modules, to be assembled at the ITER site.
  • Completed in 2022.

Its 1,250-tonne base was the first big machine part placed in the tokamak pit, in May 2020.

The cryostatIndia built the steel chamber that keeps the magnets cold.Volume16,000 cubic metresWeight3,850 tonnesMakerLarsen & Toubro, HaziraPlanShip in 54 modulesCompleted2022
The largest chamber of its kind. Original explanatory diagram.

24. What else does India supply?

India’s list goes beyond the cryostat. The Department of Atomic Energy and ITER name these items.

  • Cooling water system: it can exchange about 1 gigawatt of heat during a full-power pulse.
  • Cryogenic distribution systems.
  • In-wall shield blocks, which work as neutron shields inside the vessel.
  • Diagnostic neutral beam and other diagnostics.
  • Heating systems and their power supplies, which were at prototype and test stage in the latest IPR report.

Indian firms involved include L&T, Inox India, Tata Consulting Engineers and HCL Technologies. L&T also won a direct ITER contract for welding vacuum vessel ports.

Other Indian suppliesIndia supplies more than the cryostat.Cooling waterExchanges about 1 gigawatt of heatCryogenic linesCool the magnetsIn-wall shield blocksNeutron shields in the vesselDiagnosticsNeutral beam and othersPower suppliesAt prototype and test stage
The list goes beyond one big part. Original explanatory diagram.

25. What does India get back from ITER?

Members get 100 percent of the scientific results, though they pay only part of the cost. They also share the intellectual property.

For India there are other gains.

  • Know-how in fusion science and technology.
  • Training of a skilled workforce. About 200 people were working on site in 2025.
  • Experience that ITER says helps lay the base for an Indian fusion industry.

The government has said India may consider building a fusion reactor of its own in future, based on ITER’s experience and success.

What India getsIndia gets all the science and new skills.Science100 percentof resultsSharedintellectualpropertySkillsMagnets,cryogenics,vacuum systemsAbout 200 onsite in 2025
The gains go beyond one big part. Original explanatory diagram.
True or False: India receives only 9.1 percent of ITER's scientific results because it pays 9.1 percent.

What is India doing at home, and what does the 2016 question test?

India has its own tokamaks and its own nuclear plan. The 2016 question asks how fusion differs from that plan.

26. What are ADITYA, ADITYA-U and SST-1?

Both machines are at the Institute for Plasma Research in Gandhinagar. IPR says they are the only two tokamaks in India.

  • ADITYA is a medium-sized tokamak. It has run at IPR since 1989.
  • ADITYA-U is its upgraded version. It routinely runs experiments in support of ITER.
  • SST-1 is a superconducting tokamak. It was built for long, steady plasma pulses.

Their plasma durations have been short. An IPR director said they are only a few hundred milliseconds, far shorter than records in China and France.

India's tokamaksBoth machines are at IPR in Gandhinagar.ADITYAAt IPR since 1989ADITYA-UUpgraded, supports ITER workSST-1Superconducting, for long pulsesPulse lengthOnly a few hundred milliseconds
Both machines are at one institute. Original explanatory diagram.

27. What are India's next fusion plans?

India is thinking of an early use of fusion through a fusion-fission hybrid. In this idea a fusion core drives a sub-critical fission blanket. The Department of Atomic Energy says it could make electricity or burn radioactive waste. It would be a step while India waits for D-T results from ITER.

IPR scientists have proposed a roadmap with three steps.

  • SST-Bharat, a mid-sized machine.
  • A fusion-fission hybrid reactor.
  • A DEMO reactor of about 250 MWe, targeted for the 2060s.

This is a proposal, not an approved project.

India's next stepsThe roadmap is a proposal and not an approved project.Idea nowFusion-fission hybridStep 1SST-Bharat, a mid-sized machineStep 2Fusion-fission hybrid reactorStep 3DEMO of about 250 MWe, 2060sStatusProposal only
None of these steps is approved. Original explanatory diagram.

28. What is India's thorium plan, and how is it different?

India has limited uranium but one of the largest thorium reserves in the world. So the Department of Atomic Energy built a three-stage nuclear programme. All three stages use fission.

  • Stage 1: pressurised heavy water reactors burn natural uranium and make plutonium.
  • Stage 2: fast breeder reactors use that plutonium. They also breed uranium-233 from thorium.
  • Stage 3: reactors use uranium-233 bred from thorium.

The Prototype Fast Breeder Reactor at Kalpakkam reached first criticality on 6 April 2026. PIB says this took India into stage 2.

Thorium is a fission fuel. ITER’s success does not change it.

Thorium and ITERThe thorium plan is fission and ITER is fusion.Thorium planThree stagesAll fissionPFBR critical6 April 2026ITERFusionNot thoriumExperimentonly
Keep the two technologies apart. Original explanatory diagram.
True or False: India's three-stage nuclear programme is based on fusion.

29. What did the 2016 question ask, and why is (d) right?

UPSC Civil Services Prelims 2016, GS Paper I, Q79 asked about the “immediate advantage” for India if ITER succeeds. Option (c) is often left out of summaries.

  • (a) Use thorium in place of uranium for power generation.
  • (b) Attain a global role in satellite navigation.
  • (c) Drastically improve the efficiency of its fission reactors.
  • (d) Build fusion reactors for power generation.

(d) is the answer. ITER is a fusion test. If it works, members can design fusion power plants.

  • (a) is wrong. Thorium use is a fission matter. It belongs to India’s three-stage plan, not to ITER.
  • (b) is wrong. Satellite navigation is a different field. ITER has nothing to do with it.
  • (c) is wrong. ITER studies fusion. It does not make fission reactors more efficient.
UPSC 2016 optionsThe four options of the 2016 question.(a) Thorium for uraniumWrong: a fission matter(b) Satellite navigationWrong: not an ITER topic(c) Better fission efficiencyWrong: ITER studies fusion(d) Build fusion reactorsCorrect
The answer is the only fusion option. Original explanatory diagram.

How do you answer exam questions on ITER?

30. What are the exam traps?

Use this checklist.

  • ITER is fusion. Thorium and fast breeders are fission.
  • ITER is an experiment. It will not make electricity.
  • Location: Cadarache, southern France.
  • Seven Members: China, EU, India, Japan, Korea, Russia, US.
  • India’s share: about 9.1 percent, paid mostly in-kind.
  • India’s best-known part: the cryostat, built by L&T at Hazira.
  • Goal: Q of at least 10. That is 500 MW from 50 MW of heating.
  • Pulse goal: 400 seconds. The FAQ range is 400 to 600 seconds.
  • Fuel: deuterium and tritium. Tritium is bred from lithium.
  • The “immediate advantage” for India is the ability to build fusion reactors.
  • Say “no high-activity, long-life waste”. Do not say “no waste”.
  • Current plan: research operation 2034, D-T operation 2039.
  • Do not mix records. JET (magnetic), NIF (laser) and EAST (duration) measure different things.
Exam checklistKey facts to fix in memory.Fusion or fissionITER is fusion, thorium is fissionLocationCadarache, FranceMembersSeven, including IndiaIndia's shareAbout 9.1 percent, mostly in-kindIndia's best-known partThe cryostat, by L&TGoalQ of at least 10
State the narrow wording, not the broad one. Original explanatory diagram.

Four questions to think through

Why is the NIF result not the same as ITER's goal?

NIF counts the laser energy that reaches the fuel target. It does not count the large power drawn to run the lasers. ITER's Q compares fusion power with heating power put into the plasma. The two gains answer different questions.

Why build ITER if it will not make electricity?

ITER is built to prove the physics and the technology. It will study a burning plasma and test tritium breeding. Later machines can then turn fusion heat into power. So ITER is a step, not a power plant.

Why do ITER's cost figures differ so much?

Members build most parts themselves and need not publish what they spend. Currency rates also change the total. So a single number is risky in an exam. Say tens of billions.

Why is option (d) right and option (c) wrong in the 2016 question?

Option (c) mixes up fusion and fission. ITER studies fusion and does not tune fission reactors. Success would show that fusion plants can be designed. That is the immediate advantage, so (d) is right.

Check your understanding

Your 7 quick checksAnswered 0 of 7 · Correct 0

This score resets when the page reloads.

Continue to the 8 MCQs

✅ Test Yourself

Try 8 practice questions on ITER.

Question 1 of 8

India is an important member of the International Thermonuclear Experimental Reactor. If this experiment succeeds, what is the immediate advantage for India?
Was this helpful?

Beyond the answer

    Leave a Reply

    [privacy-do-not-sell-link]

    Discover more from MCQ Questions

    Subscribe now to keep reading and get access to the full archive.

    Continue reading

    ✨Ask doubt
    ✨ Ask a Question AI×
    [privacy-do-not-sell-link]